Where Celestavia fits in China, and three proposals
Electric carriages run on large, fixed high-strength steel cables carried by towers above the streets, rivers and hills; a nine-seat passenger cabin or a light 10-ft cargo box hangs below each carriage. 1.5 kV DC, with braking energy returned to the line.
China has the world’s largest high-speed rail and metro networks. Celestavia does not compete with them: it reaches the places they find hard — steep and river-cut cities, scenic areas that need a light footprint, and mid-size cities below the national thresholds for a metro.
| Proposal | Line | Base proposal, US$ M (P10–P50–P90) | US$ M per km, with / without stations | Passengers a day (low–base–high) | Benefit / cost (low–base–high) |
|---|---|---|---|---|---|
| Zhangjiajie | 35.0 km | 150.8–166.1–183.4 | 4.7 / 4.0 | 11,426–30,535–54,499 | 0.57–2.02–4.71 |
| Zunyi | 20.4 km | 189.1–221.9–265.0 | 10.9 / 4.9 | 67,685–162,674–279,900 | 1.28–3.52–7.56 |
| Chongqing | 7.5 km | 62.4–70.6–80.3 | 9.5 / 7.0 | 9,474–24,496–48,035 | 0.44–1.64–4.23 |
Benefit/cost at China’s 8 % social discount rate. A first-of-a-kind margin is shown beside each total, not inside it. Each proposal also comes as a lowest-price version and a full version, and every extra is priced on its own.
A film for this page will be made after the proposals are reviewed.
What China already has, and where Celestavia adds value
- Intercity travel: China's high-speed rail network is the world's largest; a light line at 70-90 km/h does not compete on intercity trips.
- The busiest city corridors: a metro line carries tens of thousands of passengers an hour each way; a two-track Celestavia line carries a few thousand with single cabins and about ten thousand with cabins coupled in threes.
- Bulk freight: rail, barges and belt conveyors move ore, coal and containers at a fraction of a heavy cable line's cost per tonne at China's volumes.
- Flat cities with wide roads: a bus rapid transit line or a tram does the job for less.
- Open-water crossings: sea links such as the bridge to the Yangshan port need towers in the water.
- Mountain and river cities: hillside districts above deep metro stations, ridges and river crossings.
- Scenic areas: a light footprint from the rail station to the park gate; the view is part of the trip.
- Mid-size cities without metro: a metro-like network for cities below the 2018 approval thresholds.
- Last-mile feeders: short links from metro and high-speed rail stations up the slopes.
- Fast, low-disruption builds: towers on small footprints, prefabricated parts, few road closures.
Roads: 59,280 deaths and 254,112 injuries were reported to the police in 2024; the World Health Organization estimates 248,099 road deaths for 2021. On the railways, the national railway administration publishes the yearly change in accident deaths (2024: down 18 %) rather than the count. Taking cars off steep, congested roads is part of each proposal’s public benefit; zero accidents is the goal of the system’s design.
Twenty places screened, three chosen for a full study
Each place was scored on terrain, the gap in today’s public transport, the size of the flows, Celestavia’s cost and build-speed edge, fit with national rules, and — as a penalty — how good the existing alternative already is. The ranking holds when the weights are changed; the three leaders stay in the top five in every case tried.
| Rank | Place | Kind | Score | What Celestavia adds |
|---|---|---|---|---|
| 1 | Zhangjiajie: high-speed rail and city to Wulingyuan | Tourism areas with heavy visitor flows | 87 | A scenic 30-minute ride from the high-speed rail station to the park gate, above the traffic, with the view as part of the trip. |
| 2 | Zunyi: hilly mid-size city without metro | Mid-size cities without metro | 84 | A metro-like network at a fraction of metro cost, built above the streets. |
| 3 | Chongqing: river-and-mountain line (Yuzhong – Yangtze – Nanshan) | Mountain and river cities | 80 | Riverside to ridge in minutes, a river crossing without a bridge, sightseeing capacity many times the old cableway's, a feeder to the metro. |
| 4 | Panzhihua: steep valley city with mines | Mid-size cities without metro | 69 | Slope-to-valley links; light cargo. |
| 5 | Shiyan: long narrow valley city | Mid-size cities without metro | 68 | A valley trunk plus Wudang Mountain visitors. |
| 6 | Guiyang: karst hills, metro feeders | Mountain and river cities | 64 | Hill-to-station feeders. |
| 7 | Huangshan: high-speed rail to the scenic area | Tourism areas with heavy visitor flows | 63 | Station-to-gate link. |
| 8 | Lijiang: old town to Jade Dragon Snow Mountain | Tourism areas with heavy visitor flows | 63 | Town-to-mountain scenic link. |
| 9 | Jiuzhaigou: new rail station to the park | Tourism areas with heavy visitor flows | 59 | Station-to-gate link. |
| 10 | Lanzhou: linear valley city, hillside estates | Mountain and river cities | 56 | Valley-floor metro to slope estates and river crossings. |
| 11 | Guilin: karst tourist city without metro | Mid-size cities without metro | 55 | A low-footprint line among the karst. |
| 12 | Mountain farm and parcel logistics (Wuling and Wumeng mountains) | Ports, mines and heavy-cargo corridors | 47 | Light boxes and passengers over gorges where roads wind for hours. |
Score out of 100. Big-city metro trunks, bulk freight and the large container ports rank last: existing systems do those jobs well.
Zhangjiajie: the city and high-speed rail to Wulingyuan
Sandstone and karst hills between the city and the park; the road winds 36 km. No rail or transit plan for the corridor; buses 40-60 min. 41.6 million tourist visits (2025); more than 60,000 a day at the Forest Park on peak days.

The line on the ground
413 towers (11.8 a km, 15 m tall on average); the ground rises from 154 to 766 m and the steepest kilometre of cable climbs 13 %. Curves sit at stations or on short rail sections (95 along the line).
Three versions, from the lowest price up
| Version | Stations | US$ M, P10–P50–P90 | US$ M/km with / without stations | First-of-a-kind margin beside | Passengers a day | Benefit / cost | Project return, base |
|---|---|---|---|---|---|---|---|
| Lowest-price proposal | 4 | 118.7–131.2–145.3 | 3.7 / 3.4 | +21.1 | 9,617–26,040–46,308 | 0.65–2.31–5.35 | 16.9 % |
| Base proposal | 8 | 150.8–166.1–183.4 | 4.7 / 4.0 | +26.7 | 11,426–30,535–54,499 | 0.57–2.02–4.71 | 14.7 % |
| Full version | 8 | 180.0–198.8–220.2 | 5.7 / 4.8 | +32.0 | 11,426–30,535–54,499 | 0.51–1.82–4.28 | 13.0 % |
Lowest-price: fewer, two-space stations and the opening-year fleet. Base: every station of the density rule, four-space small stations, megastation(s), own control centre. Full: adds waste and parcel services, emergency and monitoring package, towers ready for four tracks, own medium-voltage feeder and backup generation.
Door to door at the peak
| Trip | Car (min) | Bus or coach (min) | Celestavia (min) | Fare, CNY (resident) |
|---|---|---|---|---|
| West station -> Wulingyuan | 50 | 70 | 34 | 15.1 |
| City centre -> Wulingyuan | 78 | 108 | 44 | 18.8 |
| City centre -> West station | 36 | 50 | 19 | 6.6 |
Capacity and service
At the peak the line runs cabins that leave when their passengers are aboard and run non-stop from station to station; average seat use 6.8 of 9, walk-in wait under 3 minutes for 95 % of passengers, a fleet of 470 cabins. Two tracks carry about 12,348 passengers an hour each way with cabins coupled in threes (the base case needs 1,810; the high case 3,478). Cabins keep a braking-distance gap to the cabin ahead.
Fares, income and return
Resident fare CNY 3 plus CNY 0.45 a km (up to CNY 30); the legal reduced-fare groups pay the bus fare. Average fare CNY 19.8. Base case income: fares US$ 29.8 M a year, private-cabin bookings US$ 2.8 M, other income net of its cost US$ 2.2 M (small cells / 5g on every 4th tower, sponsorships (events, seasons, app), park-and-ride and ev charging at the megas, in-cabin seatback screens). Operating cost US$ 14.2 M a year: all income covers it 2.5 times. Fares and other income cover the operating cost and repay the capital in the base case without a public payment. In the low case it would be about US$ 12.3 M a year.
Public benefit in the base case: 4.8 million hours saved a year, about 863 car round trips off the road each day, and 1.4 road deaths and 6 injuries avoided a year. Energy: 0.10 kWh a passenger-km, 22.2 GWh a year, peak 13.9 MW.
Options, each priced on its own
| Option (against the base proposal) | US$ M, P50 | Share of the base |
|---|---|---|
| Two-space small stations instead of four-space (cheaper) | -0.1 | -0.1 % |
| Fleet and stations for the high demand case | +30.3 | +18.2 % |
| Waste collection service (CV10-W boxes, berths, carriages, transfer point) | +1.5 | +0.9 % |
| Parcels and light cargo (lockers, CV10-L boxes, carriages, sorting bay) | +1.1 | +0.7 % |
| Emergency and monitoring package (rescue, cameras, sensors) | +2.6 | +1.6 % |
| Towers and foundations ready for 4 tracks from day one | +2.8 | +1.7 % |
| Second pair of tracks later, hung on ready towers | +45.0 | +27.1 % |
| Second pair later without ready towers (second row of towers) | +50.5 | +30.4 % |
| Own medium-voltage feeder on the towers | +4.0 | +2.4 % |
| Backup generation for the peak hour (source open) | +14.2 | +8.6 % |
| Couplers for coupled cabins | +1.5 | +0.9 % |
Zunyi: Huichuan, the old town and the new district
Karst hills; the city sits on ridges and valleys at 800-1,000 m. No urban rail; buses only. A central city of a few million residents; trips concentrated on a few axes.

The line on the ground
241 towers (11.8 a km, 12 m tall on average); the ground rises from 816 to 984 m and the steepest kilometre of cable climbs 11 %. Curves sit at stations or on short rail sections (60 along the line).
Three versions, from the lowest price up
| Version | Stations | US$ M, P10–P50–P90 | US$ M/km with / without stations | First-of-a-kind margin beside | Passengers a day | Benefit / cost | Project return, base |
|---|---|---|---|---|---|---|---|
| Lowest-price proposal | 15 | 128.9–149.9–177.7 | 7.4 / 3.8 | +24.1 | 53,898–131,678–232,213 | 1.46–3.83–7.97 | 11.0 % |
| Base proposal | 26 | 189.1–221.9–265.0 | 10.9 / 4.9 | +35.7 | 67,685–162,674–279,900 | 1.28–3.52–7.56 | 9.6 % |
| Full version | 26 | 280.0–337.1–413.4 | 16.5 / 6.1 | +54.2 | 67,685–162,674–279,900 | 0.94–2.64–5.78 | 6.4 % |
Lowest-price: fewer, two-space stations and the opening-year fleet. Base: every station of the density rule, four-space small stations, megastation(s), own control centre. Full: adds waste and parcel services, emergency and monitoring package, towers ready for four tracks, own medium-voltage feeder and backup generation.
Door to door at the peak
| Trip | Car (min) | Bus or coach (min) | Celestavia (min) | Fare, CNY (resident) |
|---|---|---|---|---|
| Huichuan north -> old town | 43 | 60 | 18 | 4.4 |
| Old town -> new district | 41 | 58 | 20 | 5.7 |
| Huichuan north -> new district | 76 | 105 | 30 | 7.6 |
Capacity and service
At the peak the line runs timetabled line cabins that call at the stations along the way, coupled in threes at the busiest times; average seat use 7.5 of 9, walk-in wait under 1 minutes for 95 % of passengers, a fleet of 417 cabins. Two tracks carry about 11,134 passengers an hour each way with cabins coupled in threes (the base case needs 5,516; the high case 10,110). Cabins keep a braking-distance gap to the cabin ahead.
Fares, income and return
Resident fare CNY 2.5 plus CNY 0.25 a km (up to CNY 8); the legal reduced-fare groups pay the bus fare. Average fare CNY 3.3. Base case income: fares US$ 23.6 M a year, private-cabin bookings US$ 2.2 M, other income net of its cost US$ 3.7 M (in-cabin seatback screens, app / digital advertising, booking and marketplace fees in the app, sponsorships (events, seasons, app)). Operating cost US$ 14.1 M a year: all income covers it 2.1 times. In the base case an availability payment of about US$ 1.0 M a year lifts the project return to 10 %. In the low case it would be about US$ 18.1 M a year.
Public benefit in the base case: 20.3 million hours saved a year, about 8,369 car round trips off the road each day, and 4.9 road deaths and 21 injuries avoided a year. Energy: 0.09 kWh a passenger-km, 20.3 GWh a year, peak 12.2 MW.
Options, each priced on its own
| Option (against the base proposal) | US$ M, P50 | Share of the base |
|---|---|---|
| Two-space small stations instead of four-space (cheaper) | +0.0 | +0.0 % |
| Fleet and stations for the high demand case | +111.6 | +50.3 % |
| Waste collection service (CV10-W boxes, berths, carriages, transfer point) | +3.7 | +1.7 % |
| Parcels and light cargo (lockers, CV10-L boxes, carriages, sorting bay) | +2.0 | +0.9 % |
| Emergency and monitoring package (rescue, cameras, sensors) | +1.9 | +0.9 % |
| Towers and foundations ready for 4 tracks from day one | +1.4 | +0.6 % |
| Second pair of tracks later, hung on ready towers | +126.4 | +57.0 % |
| Second pair later without ready towers (second row of towers) | +129.2 | +58.2 % |
| Own medium-voltage feeder on the towers | +3.0 | +1.3 % |
| Backup generation for the peak hour (source open) | +12.5 | +5.7 % |
| Couplers for coupled cabins | +0.0 | +0.0 % |
Chongqing: Yuzhong, across the Yangtze, up to Nanshan
Two rivers and a 400-680 m ridge beside the centre; the riverside escarpment rises about 230 m in a kilometre. Over 600 km of urban rail, but no station serves the Nanshan ridge; the 1987 Yangtze cableway (one 66-place cabin each way) has queues. 470 million domestic tourist visits (2024) and the cableway's 4 million passengers a year show the flow; hillside residents add daily trips.

The line on the ground
87 towers (11.7 a km, 18 m tall on average); the ground rises from 168 to 537 m and the steepest kilometre of cable climbs 12 %. Curves sit at stations or on short rail sections (21 along the line). It crosses the Yangtze River bank to bank in one long span.
Three versions, from the lowest price up
| Version | Stations | US$ M, P10–P50–P90 | US$ M/km with / without stations | First-of-a-kind margin beside | Passengers a day | Benefit / cost | Project return, base |
|---|---|---|---|---|---|---|---|
| Lowest-price proposal | 5 | 39.6–44.6–50.6 | 6.0 / 4.9 | +7.2 | 7,700–19,276–37,907 | 0.44–1.64–4.19 | 29.6 % |
| Base proposal | 7 | 62.4–70.6–80.3 | 9.5 / 7.0 | +11.4 | 9,474–24,496–48,035 | 0.44–1.64–4.23 | 23.2 % |
| Full version | 7 | 79.1–89.6–102.2 | 12.0 / 8.5 | +14.4 | 9,474–24,496–48,035 | 0.38–1.44–3.75 | 19.9 % |
Lowest-price: fewer, two-space stations and the opening-year fleet. Base: every station of the density rule, four-space small stations, megastation(s), own control centre. Full: adds waste and parcel services, emergency and monitoring package, towers ready for four tracks, own medium-voltage feeder and backup generation.
Door to door at the peak
| Trip | Car (min) | Bus or coach (min) | Celestavia (min) | Fare, CNY (resident) |
|---|---|---|---|---|
| Jiefangbei -> Nanshan viewpoints | 45 | 63 | 15 | 5.5 |
| Jiefangbei -> Huangjueya | 50 | 70 | 16 | 6.0 |
| Shangxinjie metro -> Huangjueya | 34 | 47 | 14 | 5.0 |
| Xiaoshizi -> Botanical Garden | 52 | 73 | 17 | 6.4 |
Capacity and service
At the peak the line runs cabins that leave when their passengers are aboard and run non-stop from station to station; average seat use 6.0 of 9, walk-in wait under 3 minutes for 95 % of passengers, a fleet of 135 cabins. Two tracks carry about 13,812 passengers an hour each way with cabins coupled in threes (the base case needs 1,995; the high case 4,192). Cabins keep a braking-distance gap to the cabin ahead. About 7,726 visitors a day ride the river-and-ridge loop for the view (CNY 30 return).
Fares, income and return
Resident fare CNY 3 plus CNY 0.5 a km (up to CNY 10); the legal reduced-fare groups pay the bus fare. Average fare CNY 15.2. Base case income: fares US$ 18.8 M a year, private-cabin bookings US$ 0.7 M, other income net of its cost US$ 5.0 M (packages and passes (ski / park / attraction bundles), sightseeing / attraction tickets and events, sponsorships (events, seasons, app), in-cabin seatback screens). Operating cost US$ 7.5 M a year: all income covers it 3.3 times. Fares and other income cover the operating cost and repay the capital in the base case without a public payment. In the low case it would be about US$ 1.0 M a year.
Public benefit in the base case: 2.8 million hours saved a year, about 567 car round trips off the road each day, and 0.3 road deaths and 1 injuries avoided a year. Energy: 0.12 kWh a passenger-km, 5.2 GWh a year, peak 4.4 MW.
Options, each priced on its own
| Option (against the base proposal) | US$ M, P50 | Share of the base |
|---|---|---|
| Two-space small stations instead of four-space (cheaper) | -0.0 | -0.1 % |
| Fleet and stations for the high demand case | +14.2 | +20.1 % |
| Waste collection service (CV10-W boxes, berths, carriages, transfer point) | +1.5 | +2.1 % |
| Parcels and light cargo (lockers, CV10-L boxes, carriages, sorting bay) | +1.0 | +1.5 % |
| Emergency and monitoring package (rescue, cameras, sensors) | +1.2 | +1.7 % |
| Towers and foundations ready for 4 tracks from day one | +0.8 | +1.1 % |
| Second pair of tracks later, hung on ready towers | +20.3 | +28.8 % |
| Second pair later without ready towers (second row of towers) | +21.8 | +30.9 % |
| Own medium-voltage feeder on the towers | +2.1 | +2.9 % |
| Backup generation for the peak hour (source open) | +4.5 | +6.3 % |
| Couplers for coupled cabins | +0.4 | +0.6 % |
Celestavia beside other systems built in China
| System | km | US$ M per km | Peak passengers an hour each way | Source |
|---|---|---|---|---|
| Celestavia Zhangjiajie (base proposal) | 35.0 | 4.7 (4.0 without stations) | 12,348 two tracks, cabins coupled in threes | Celestavia study, 22 Nov 2026 |
| Celestavia Zunyi (base proposal) | 20.4 | 10.9 (4.9 without stations) | 11,134 two tracks, cabins coupled in threes | Celestavia study, 22 Nov 2026 |
| Celestavia Chongqing river-and-mountain line (base proposal) | 7.5 | 9.5 (7.0 without stations) | 13,812 two tracks, cabins coupled in threes | Celestavia study, 22 Nov 2026 |
| Urban rail under construction in China, average | – | 119.9 | 30,000 metro approval threshold (long-term peak flow) | CAMET, Urban Rail Transit 2025 Annual Statistics and Analysis Report (2025) |
| Modern tram, average of 34 Chinese lines | – | 21.6 | – | China News Service (中新网), report on Chinese tram lines (2 Feb 2024) (2023) |
| Automated rubber-tyred line, Chongqing Bishan (2021) | 15.4 | 17.4 | 10,000 upper bound of the product class | Jiemian (界面新闻), 2021 (2021) |
| Straddle monorail, Chongqing Line 3 | 67.0 | – | 32,000 capacity; cost scope unclear in the source | railway-technology.com / Railway Gazette (search-result summary) (2019) |
| Suspended monorail, Wuhan Optics Valley (2023) | 10.5 | – | – 220 passengers a train; cost not published | Wikipedia 'Optics Valley Suspended Monorail'; Jiemian 2023 (2023) |
| Bus rapid transit, Guangzhou (infrastructure only) | 22.5 | 4.5 | – about 800,000 boardings a day | ITDP, Guangzhou BRT article (Mar 2010); development.asia case study (2010) |
| Aerial cableway, Chongqing Yangtze River (1987) | 1.2 | – | – two cabins of 65 passengers; over 4 million passengers a year | China News Service (6 Feb 2018) (2017) |
| Aerial cableway, Tianmen Mountain, Zhangjiajie (2005) | 7.5 | – | 1,000 about 1,000 an hour (travel sources; uncertain) | Wikipedia 'Tianmen Mountain' (2005) |
| Mountain tourist railway, Dujiangyan – Siguniang (building) | 123.2 | 24.2 | – cost a lower bound ('over CNY 20 bn') | Sichuan Online / 川观新闻 (27 Sep 2020) (2020) |
A metro or a straddle monorail carries far more people an hour than a two-track Celestavia line, and is the right choice for a city’s busiest trunk. Celestavia’s case is a lower cost per km on steep or river-cut ground, towers on small footprints instead of tunnels or viaducts, stations every few hundred metres, direct cabins, and lines that grow a cabin at a time. Costs from different years are shown as published (converted at CNY 6.71 per US$).
Why heavy cargo lines are not proposed in China
China moves ore, coal and containers by rail, barge, belt conveyor and truck at very low rates. A two-lane Celestavia heavy line at about US$ 17 M a km would cost, for its capital alone, about CNY 1.98 a tonne-km at 5 million tonnes a year — 5 times the road freight rate of about CNY 0.40 — and would match road freight only above roughly 25 million tonnes a year. Heavy lines fit China only as short links from a mine to a railhead where no road can be built. Light 10-ft boxes for parcels and farm produce on the passenger lines are offered as an option on each proposal.
Electric, 1.5 kV DC, with the source left open
Each line takes 1.5 kV DC from substations along it, on two contact wires; the cables carry no current. Braking energy goes back to the line, or to an on-board braking resistor when the line cannot take it. The three base proposals together use about 48 GWh a year. The source is a choice: the city grid, the line’s own medium-voltage feeder on the towers, or backup generation — each priced as an option. Every tower carries a battery for at least 21 days of sensors, cameras and communications without grid power.
Heat, fog, storms, freezing rain and earthquakes
Operation steps down in levels — full, partial, secured, rescue — as wind, ice or seismic sensors on every tower report. Summer heat in Chongqing sets the cabin air-conditioning load counted in the energy figures; winter freezing rain on the Guizhou plateau (Zunyi) sets the icy-cable case for the steepest grades; passenger service stops at the operating gust limit and cabins are brought to stations. Towers are sized for the local seismic code. Fibre, 5G and cameras along the line report every tower and cabin to the control centre.
Jobs
Building the lines brings work to local crews and suppliers of foundations, steel, cables and electrical works; operating them creates lasting skilled jobs in operation, maintenance and passenger service, with training. Cables, motors, cabins and their materials draw on China’s manufacturing industry.
First passengers in under five years
Our goal is five years or less from approval to first service. Approvals set the pace; where the government runs studies, permits and land in parallel, design starts at once and the type approval comes from the test line, each line opens in about two and a half years.
| Proposal | First service, median | First service, 90th percentile | Whole line, median |
|---|---|---|---|
| Zhangjiajie | Apr 2029 | Jul 2029 | Apr 2029 |
| Zunyi | Apr 2029 | Jul 2029 | Apr 2029 |
| Chongqing | Apr 2029 | Jul 2029 | Apr 2029 |
Months counted from January 2027.
The choices are yours
- Which proposal first: tourism (Zhangjiajie), a mid-size city without metro (Zunyi), or a mountain and river city (Chongqing) — or a demonstration line in one of them.
- Which version: lowest-price, base or full, and each option above on its own.
- Financing: a concession with the public side’s land and right of way in kind, development banks, an availability payment where a line serves public goals beyond its fares, or a public–private partnership. The local Celestavia company operates the lines.
- Other places: Guiyang, Lanzhou, Shiyan, Panzhihua, Huangshan and Lijiang ranked next; the same study can be run for any city.
Celestavia designs the system, its electronics and software, and brings the partners together; towers, cabins, carriages and buildings are made and built by contracted suppliers, many of them in China.
- Method: for each line, today’s door-to-door trips by car, taxi, bus, coach, metro, motorcycle and on foot are compared with the trip by Celestavia; capacity, fleet and stations follow from the peak hour; cost ranges come from thousands of draws of every unit price; the return and the benefit/cost use one method for every country. Alignments are drawn on the terrain model between existing places and are not surveyed.
- National Bureau of Statistics (Statistical Communiqué 2025; China Statistical Yearbook 2025); China State Railway Group and National Railway Administration (2025); China Association of Metros, annual report 2025; State Council General Office document No. 52 (2018); Ministry of Public Security (2025); Ministry of Culture and Tourism (2025); World Health Organization, Global status report on road safety 2023; Ministry of Ecology and Environment (grid emission factor, 2023); China Foreign Exchange Trade System (19 Nov 2026).
- Chongqing Municipal Bureau of Statistics (2025); Chongqing tourism figures (2024); China News Service and The Paper (Yangtze River cableway); Zhangjiajie statistics as reported by Hunan Daily (2025); CAAC airport statistics (2025); Wikipedia and Wikidata for station positions; Zunyi 2020 census; Amap traffic report (2024).
- Costs of other systems: CAMET (2025), China News Service (trams, 2023), Jiemian (Bishan line, 2021), ITDP (Guangzhou BRT, 2010), Sichuan Online (Dujiangyan – Siguniang railway, 2020). Terrain: Copernicus GLO-30 (European Space Agency).
- Data to request later: city travel surveys, bus passenger counts by line, visitor counts by gate, local unit prices and supplier quotes.
Projections, not guarantees: every project figure on this page is simulated for this concept study (22 November 2026); costs are ranges until suppliers quote.
© Global Genius Trust y Celestavia Co.
Join us
Join Celestavia
Public authorities, transport operators, business people and the general public are invited to learn about the proposal, share their ideas and join in. Sign up and we will keep you posted on the project.